181. Which of the following are key components of a Total Quality Management system?

A. Individual responsibility, incremental improvement, use of raw data

B. Collective responsibility, continual improvement, use of raw data

C. Group responsibility, staged improvement, knowledge

D. Involves everyone, continual improvement, use of data and knowledge

182. What is the term for the monitoring of events both internal and external to the organisation that affects strategy?

A. Operational control

B. Strategic surveillance

C. Strategic control

D. Environmental scanning

183. When a manager monitors the work performance of workers in his department to determine if the quality of their work is ‘up to standard’, this manager is engaging in which function?

A. Planning

B. Controlling

C. Organising

D. Leading

184. “How will conflicts over resources/facility usage between this and other projects be settled?”, is critically settled at level

A. Main program

B. Project formation

C. Project Buildup

D. Project Buildup

185. Level which includes disposition of project’s assets and personnel, is

A. First Stage

B. Second Stage

C. Third stage

D. Fourth stage

186. A mean for monitoring and controlling organization’s strategic projects is

A. Project Monitoring process

B. Project Portfolio Process

C. Project Portfolio Plan

D. Project Portfolio Phase

187. Projects provide an excellent growth environment for future executives and for developing

A. Sales skills

B. Manufacturing skills

C. Managerial skills

D. Execution skills

188. Favored technique for resolving conflict is

A. Negotiating

B. Conciliation

C. Removal of participants

D. Not entertaining them

189. What is the critical path through the network above?

A. ABGHIF

B. ABDEF

C. ABGHIF& ABDEF

D. ABCEF

190. What would be the critical path if the duration of activity C increased to 10?

A. ABCF

B. ABCEF

C. ABGHIF

D. ABGHIF & ABDEF